普侨直流在世界上首次实施无接地极运行

来源:新能源网
时间:2024-08-16 22:49:15
热度:

普侨直流在世界上首次实施无接地极运行.TRS_Editor P{margin-top:0;margin-bottom:1.5em;line-height:2;font-family

.TRS_Editor P{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor DIV{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor TD{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor TH{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor SPAN{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor FONT{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor UL{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor LI{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}.TRS_Editor A{margin-top:0;margin-bottom:1.5em;line-height:2;font-family:宋体;font-size:10.5pt;}

  9月28日5时20分,南方电网第二条±800千伏特高压直流——普侨直流,正式进入普洱侧无接地极双极运行模式,输送功率3000兆瓦。普侨直流采用无接地极双极运行方式,提高了直流线路的输送能力,降低了功率损耗,对保障汛期云南水电送出、减少弃水,缓解广东地区用电高峰的电力缺口,充分发挥南方电网资源优化配置作用具有重要意义。

  据悉,10月1-10日,国庆节期间及因受普洱地震影响,普侨直流暂停实施无接地极双极运行模式,震后,超高压公司组织对普侨直流受地震影响范围内的设备、线路开展特巡,暂未发现影响运行的重大缺陷隐患。10日6时23分,调度下令将普侨直流再次转为普洱侧无接地极特殊运行方式,目前系统运行正常。据了解,特殊方式运行时间视云南侧水情而定,暂无明确时间表。

  据介绍,该运行方式是以站内接地网作为接地端的全新模式,对送端普洱站的入地电流、地电位抬升、跨步电压、控制保护系统响应、对一次设备性能影响等各类问题均有较高的要求。此前,南方电网公司高度重视相关调试与准备工作,从前期可行性研究、各项技术研究报告编制、控制保护软件修改仿真,以及调试方案策划,都进行了多方研究与充分验证。

  超高压公司有效组织开展了普侨直流无接地极运行准备工作:妥善部署前期准备工作,明确各局在无接地极运行期间的工作要求,组织开展运行方案、调度规程、现场运规及应急处置预案的培训、考核及模拟演练,确保现场人员掌握运维要求并做好应急准备。9月28日当天上午,超高压公司副总经理赵建宁一行赶赴侨乡换流站,对普侨直流特殊运行方式下的运维工作进行了专项检查与指导。赵建宁强调,运行工作要结合现场实际情况有针对性、有侧重点地开展,运行人员在开展业务联系时须做好记录,避免出现交接不清、责任不明的情况。

  为确保无接地极双极安全运行,普洱换流站、侨乡换流站加强出入生产区域人员管理,针对外来施工和后勤人员开展安全教育,把安全警示工作一一落实到位。按照分层、分级、分类管控的运维策略对站内的人身和设备风险进行分析,制定行之有效的管控策略。加大高温高负荷特巡频率,分析多维度数据,全面掌握站内设备运行状态。(陈云亭 张强 王晨涛)